For FICO - Production planning the integration is mainly in
controlling area - Primary cost element , secondary cost
element , activity cost and cost centre .

PP-FICO inteegartion
A.
1. Activity type you have to define in PP area , thse
activity handover to FI consultant.
2. FI consultant assign prizing to this activity ,
3. Then you assign this activity in your workcenter
4. Assign cost center in work center , take this cost
center from FI
===> From this plaaned cost calculate , formula from work
center, values from routings and prize from FI , flow
completed.

B.
1. Define valuation varrient in order type dependent
parameter i.e opl8 in controlling tab page.- SPRO
2. take this valuation varrient from FI
3. Discuus the REL strategy with FI during costing sheet
preaparation with FI
4. Take controlling area from FI
5. Costing varrient , varriance key in order type SPRO
6. Settelement profile
7. Disccus when FI want to calculate actual cost at REl ,
8. If the process is REM- then product cost collector -
KKF6N for your proper production version
9. In REM process - product costing CK11N and CK24 monthly.
10.Actual varrient 007 and planned varrient from costing
sheet.
11. In control key configurataion costing check box- OP67

Download SAP FI CO Interview Questions And Answers PDF

Previous QuestionNext Question
What are the tools for solving tickets in sap fico?Is standard cost estimate with
out quantity structure, and what is the configuration settings for that?