Inspector Quality Assurance/QC Question:
Download Questions PDF

Explain what is final RFI? When it shall be raised up?

Answer:

When the QA/QC department of contractor is satisfied that the work detailed in the construction RFI is completed, then request shall be submitted for inspection to the client QA/QC department.

Download Quality Assurance Interview Questions And Answers PDF

Previous QuestionNext Question
Explain what are QA/QC's ITP's and QCP? Give a brief?Tell me what are the required documents for a local loop folder?