Manager Construction Question:

Which time results in the leasi, possible construction cost of an activity, is known:

A. normal time
B. slow time
C. crash time
D. standard time

Construction Manager Interview Question
Construction Manager Interview Question

Answer:

B. slow time


Previous QuestionNext Question
The Modular co-ordination of construction proper means?
A. planning
B. designing
C. execution
D. all the above
Pick up correct statement from following:
A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C. CPM does not make any allowance for the uncertainties in the duration of time
D. In CPM, the time is related to cost
E. All the above