Manager Construction Question:

The Time by which activity completion time can be delayed without affecting start of succeeding activities, is known as:

A. duration
B. total flat
C. free float
D. interfering float

Construction Manager Interview Question
Construction Manager Interview Question

Answer:

C. free float


Previous QuestionNext Question
The Critical Path of Net Work helps an engineer:

A. to concentrate his attention on critical activities
B. to divert the resources from non-critical advanced activities to critical activities
C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. all the above
Artificial activity which indicates an activity following it, cannot be started unless the preceding activity is complete, is known as:

A. event
B. free float
C. dummy
D. constant