Manager Construction Question: The Bar charts are suitable for: A. minor works B. major works C. large projects D. all the Above Construction Manager Interview QuestionAnswer: A. minor works Previous QuestionNext QuestionIf total float and duration of activity are 5 and 10 days respectively, the particular activity can be: A. started 5 days later B. completed 5 days later C. performed at slower rate in 15 days D. all the aboveCritical ratio scheduling: A. establishes the relative priorities among various activities on a common basis B. determines the status of each activity C. adjusts automatically changes in activity progress D. is a dynamic system E. none of these