Prior to using an electric saw on a construction site, a user check finds that the insulation on the supply flex is damaged. The correct procedure would be to

Answer:
* a) Replace the cord with a new one
* b) Report the damage to a supervisor after use
* c) Repair the cord with insulation tape
* d) Report the damage to a supervisor before use
Answer – d