Manager Construction Question:

Pick up correct statement from following:
A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C. CPM does not make any allowance for the uncertainties in the duration of time
D. In CPM, the time is related to cost
E. All the above

Construction Manager Interview Question
Construction Manager Interview Question

Answer:

E. All the above


Previous QuestionNext Question
Which time results in the leasi, possible construction cost of an activity, is known:

A. normal time
B. slow time
C. crash time
D. standard time
The Works costing less than Rs. 20,000 are treated as:

A. projects
B. major projects
C. minor projects
D. all the above