Manager Construction Question:

Overall in-charge of organisation at site responsible for the execution of the works, is:

A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Sub overseer
E. Assistant Engineer

Construction Manager Interview Question
Construction Manager Interview Question

Answers:

Answer #1
B. Engineer

Answer #2
Engineer


Previous QuestionNext Question
If TL is the latest allowable event occurrence time, total activity slack(s), is equal to:

A. LST-EST
B. LFT-EFT
C. TL-EFT
D. all the above
The Modular co-ordination of construction proper means?
A. planning
B. designing
C. execution