Manager Construction Question:

Method of Critical path:

A. is an improvement upon bar chart method
B. provides a realistic approach to daily problems
C. avoids delays which are very common in bar charts
D. was invented by Morgan R. Walker of Dupot and James E. Kalley or Remington U.S.A. in 1957
E. All the above

Construction Manager Interview Question
Construction Manager Interview Question

Answer:

E. All the above


Previous QuestionNext Question
Functional organisation of salient feature is:

A. strict adherence to specifications
B. separation of planning and design part
C. each individual maintains functional efficiency
D. work is properly planned and distributed
E. all the above
The Critical Path of Net Work helps an engineer:

A. to concentrate his attention on critical activities
B. to divert the resources from non-critical advanced activities to critical activities
C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. all the above