Manager Construction Question:

If total float and duration of activity are 5 and 10 days respectively, the particular activity can be:

A. started 5 days later
B. completed 5 days later
C. performed at slower rate in 15 days
D. all the above

Construction Manager Interview Question
Construction Manager Interview Question

Answer:

D. all the above


Previous QuestionNext Question
The Works costing less than Rs. 20,000 are treated as:

A. projects
B. major projects
C. minor projects
D. all the above
The Bar charts are suitable for:

A. minor works
B. major works
C. large projects