Manager Construction Question:

If TL is the latest allowable event occurrence time, total activity slack(s), is equal to:

A. LST-EST
B. LFT-EFT
C. TL-EFT
D. all the above

Construction Manager Interview Question
Construction Manager Interview Question

Answer:

D. all the above


Previous QuestionNext Question
First method invented for planning projects, was:
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Programme Evaluation and Review Technique (PERT)
Overall in-charge of organisation at site responsible for the execution of the works, is:

A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Sub overseer
E. Assistant Engineer