Estimated time required to perform activity, is known as:

A. event
B. dummy
C. duration
D. float

Construction Manager Interview Question
Construction Manager Interview Question

Answer:

C. duration


Previous QuestionNext Question
The Site order book is used for the recording:

A. instructions by the executive engineers
B. construction measurements
C. issue of store equipments
D. names of the casual labour
CPM family is includes:

A. CPA (Critical Path Analysis)
B. CPP (Critical Path Plotted)
C. MCE (Minimum Cost Expenditure)
D. CPS (Critical Path Scheduling)