Manager Construction Question:

CPM is the:

A. synthesising in concepts
B. is built of activities oriented programme
C. is based on time estimate
D. is used for repetitive works
E. all the above

Construction Manager Interview Question
Construction Manager Interview Question

Answer:

E. all the above


Previous QuestionNext Question
The Critical path lies along activities having total float:

A. positive
B. negative
C. zero
D. same
Construction schedule is prepared after collecting:

A. number of operations
B. output of labour
C. output of machinery
D. quantity of various items
E. all the above.