Question:
While reviewing the progress, the project manager assesses that the activity has been missed out from the implementation plan. The milestone, scheduled to be achieved within another week, would be missed with the current implementation plan.

Option A):
Assess alternatives to meet the milestone
Option B):
Report the error and the planned recovery actions
Option C):
Report the error and the expected delay
Option D):
Omit the status update on the milestone

Correct Answer is Option A):
Assess alternatives to meet the milestone


Online Web Tutorials And Interview Questions With Answers Forum:
https://globalguideline.com/forum/

2018-07-16 07:44:26

Advertisement
Ads By Google

Re: Project Management Quiz MCQs Quiz Question.



\n

Board footer