Question:
The cost variance is positive and the schedule variance is also positive, then it indicates that
Option A):
Project is under budget and behind schedule
Option B):
Project is over budget and ahead of schedule
Option C):
Project is over budget and behind schedule
Option D):
Project is under budget and ahead of schedule
Correct Answer is Option A):
Project is under budget and behind schedule