‘A’ can do a piece of work in 20 days, ‘B’ in 15 days and ‘C’ in ...
Law Mathematics Exams Quizzes MCQs Quizzes Law Mathematics Test 2
Question:
‘A’ can do a piece of work in 20 days, ‘B’ in 15 days and ‘C’ in 12 days. In how many days can ‘A’ finish the work if he is assisted by ‘B’ on one day and ‘C’ on the next, alternately?
Option A):
10
Option B):
14
Option C):
6
Option D):
8
Correct Answer is Option B):
14