Construction Management Quiz Question.
Civil Engineering Quizzes Construction Management
Question:
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
Option A):
3
Option B):
4
Option C):
2
Option D):
1
Correct Answer is Option D):
1