36 Payables Management Questions and Answers:
1 :: The Final technical authority of a project lies with:
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer
D. Chief Engineer
Post Your Answer
2 :: Performance of a specific task in CPM, is known:
A. Dummy
B. Event
C. Activity
D. Contract
C. Activity
Post Your Answer
3 :: Construction team means:
A. an engineer
B. an architect
C. an owner
D. a contractor
E. all the abov
E. all the above
Post Your Answer
4 :: CPM is a:
A. synthesizing in concepts
B. is built of activities oriented program
C. is based on time estimate
D. is used for repetitive works
E. all the above
E. all the above
Post Your Answer
5 :: Construction schedule is prepared after collecting:
A. number of operations
B. output of labor
C. output of machinery
D. quantity of various items
E. all the above
E. all the above
Post Your Answer
6 :: Dummy activity:
A. is artificially introduced
B. is represented by a dotted line
C. does not consume time
D. all the above
D. all the above
Post Your Answer
7 :: The Military organisation is known as:
A. line organisation
B. line and staff organisation
C. functional organisation
D. none of these
A. line organisation
Post Your Answer
8 :: Completion of activity on CPM network diagram, is generally known:
A. Event
B. Node
C. Connector
D. All the above.
D. All the above
Post Your Answer
9 :: Milestone chart:
A. shows the inter-dependencies of various jobs
B. depicts the delay of jobs, if any
C. points outgoing ahead of schedule of jobs, if any
D. none of these.
D. none of these
Post Your Answer
10 :: Pick up correct statement from the following:
A. The float may be positive, zero or negative
B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project
D. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
E. All the above.
E. All the above
Post Your Answer