SAP MM Question:
Download Questions PDF

We want to change some data like price, data etc in created purchase order. But system is not allowing the same. As a support SAP MM functional consultant what you would do?

Answer:

There are settings available in release indicator, saying
that, no changes can be applicable once released. If u do
want to do changes, you need to set the release indicator
settings as 'CHANGABLE AFTER RELEASE' option

Download SAP MM Interview Questions And Answers PDF

Previous QuestionNext Question
I have created schedule line for one PO that delivery date
for some qty is for eg.20th of dec9.but vendor delivered before that is it possible to post GR? AND actualy why we need to maintain scheduling agreements?
What is the interaction between SAP MM and SAP ABAP consultant and How does they interact?