The Critical path method:
A. is an improvement upon bar chart method
B. provides a realistic approach to daily problems
C. avoids delays which are very common in bar charts
D. was invented by Morgan R. Walker of Dupot and James E. Kalley or Remington U.S.A. in 1957
E. All the above

Answer:

E. All the above

Download Payables Management Interview Questions And Answers PDF

Previous QuestionNext Question
The Critical Path Net Work helps an engineer:
A. to concentrate his attention on critical activities
B. to divert the resources from non-critical advanced activities to critical activities
C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. all the above
Executive Engineer may have powers upto:
A. Rs. 25,000
B. Rs. 50,000
C. Rs. 100,000
D. Rs. 200,000
E. Rs. 500,000