SAP MM Question:
Download Questions PDF

I have created schedule line for one PO that delivery date
for some qty is for eg.20th of dec9.but vendor delivered before that is it possible to post GR? AND actualy why we need to maintain scheduling agreements?

Answer:

If the Sch.line is created in date format, then GR cannot
be prepared before the scheduled date.

Scheduling agreements is released to vendor only as an qty
indication.