First method invented for planning projects, was:
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Program Evaluation and Review Technique (PERT)

Answer:

A. Bar chart method

Download Payables Management Interview Questions And Answers PDF

Previous QuestionNext Question
Time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as:
A. duration
B. total flat
C. free float
D. interfering float
Overall in-charge of an organisation at the site responsible for the execution of the works, is:
A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Sub overseer
E. Assistant Engineer