Explain Which business constraint poses the greatest potential risk to completing your project for Blue
Yonder Airlines?
A. The current IT staff must support the solution in the future
B. All testing scenarios and all necessary rework must be completed during the one-month testing
period.
C. The scheduling vendor will begin providing access by XML Web service in three months
D. The application must be completed within a five-month development period before it is tested
Answer:
C. The scheduling vendor will begin providing access by XML Web service in three months