PMI Certification Exam Question:
Download Questions PDF

Explain The PERT method is MOST used in situations where:
A. It is important to know the interrelationships of activities.
B. Little is known about the cost estimated related to the project.
C. Little experience exists on which to base estimated of activity duration.
D. Resource requirements are well defined.

Answer:

C. Little experience exists on which to base estimated of activity duration.

Download PMI Certification Interview Questions And Answers PDF

Previous QuestionNext Question
Explain an ideal situation resource leveling should be limited to activities with___?
A. With zero float time.
B. With negative float time.
C. With positive float time.
D. With critical float time
E. On the critical path.
Suppose A primary function of the change control board is to:
A. Review the impact of change request.
B. Issue change requests.
C. Represent top management interests.
D. Identify new areas of project work.
E. Assign new team members to increase output.