PMI Certification Exam Question:
Download Questions PDF

As the project manager, which of the following techniques would you employ to control the project
schedule?
A. Pareto diagram.
B. Statistical sampling.
C. Performance measurement.
D. Parametric modeling.
E. All of the above.

Answer:

C. Performance measurement.

Download PMI Certification Interview Questions And Answers PDF

Previous QuestionNext Question
The person responsible for obtaining funding for a new project?s conceptual study is the:
A. Project manager.
B. President.
C. Chief financial officer.
D. Project sponsor.
E. The client
Explain Which of the following represents the BEST way to organize project activities for scheduling?
A. By the critical path.
B. By the task start date.
C. By the date of commencement of project.
D. By work breakdown structure.
E. By the responsible organization.